Consent to spend
Contents |
[edit] Introduction
In construction the term 'consent to spend' is sometimes referred to as an ‘if’ contract. A letter with instructions to proceed and consent to spend allows work to proceed up to a certain value while the contract itself is still being drafted. The consent to spend letter can be a legally binding contract that pre-dates the principal contract. Once the principal contract is signed the consent to spend letter can be superseded. Consent to spend can also be captured in a letter of intent.
[edit] Consent to spend letter contents
It is good practice to capture as a minimum the following items in a consent to spend letter:
- The parties involved in the contract.
- A description of the works required to avoid ambiguity.
- A statement of the intention of the parties to enter into a formal contract.
- The price, or if the price is not known, established rates can be mentioned or the contract administrator can detail specific requirements to ensure financial control.
- The maximum expenditure limit relating to the consent to spend contract.
- The date of possession and access to site.
- The completion date if known.
- The contract administrator can refer to a short-term program.
- There might be sectional completion requirements that can be listed.
- Insurance requirements.
- Termination procedure.
- Confirmation that the contract created by the consent to spend will be terminated by the principle contract.
It is advisable to capture as much detail as possible in the letter of consent to spend. The letter can be a great advantage to the construction program, but the risk of not capturing details or covering basic clauses can result in problems.
[edit] An alternative to a consent to spend or letter of intent
An employer can use a pre-construction service agreement (PCSA) if they need the input of a contractor before the construction contract is in place. A pre-construction service agreement is a contract commonly used in two-stage tendering. Two stage tendering involves the employer tendering the project on the basis of an incomplete design. A contractor is then chosen to work with the employer based on its proposal for the pre-construction second stage of the tender.
The employer might want the contractor’s input on programming, designs and buildability prior to issuing the construction contract. In the right circumstances, a PCSA can be beneficial to both parties and bring design improvements and costs savings, and encourage a strong working relationship. A letter of intent/consent to spend is not likely to achieve the same benefits as a PCSA. A PCSA is however a formal agreement and a small-scale project might not have the budget or program to accommodate this type of formal agreement.
[edit] Conclusion
A consent to spend letter can be a good tool to expedite work on site but contract administrators need to be aware of the legal implications to avoid unnecessary risk to the project.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
The Remarkable Pinwill Sisters: from ‘lady woodcarvers’ to professionals. Book review.
Skills gap and investment returns on apprenticeships
ECA welcomes new reports from JTL Training and The Electrotechnical Skills Partnership.
Committee report criticises UK retrofit schemes
CIOB responds to UK’s Energy Security and Net Zero Committee report.
Design and construction industry podcasts
Professional development, practice, the pandemic, platforms and podcasts. Have we missed anything?
C20 Society; Buildings at Risk List 2025
10 more buildings published with updates on the past decade of buildings featured.
Boiler Upgrade Scheme and certifications consultation
Summary of government consultation, closing 11 June 2025.
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
From project managers to rising stars, sustainability pioneers and more.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.